Blog › Building your house · 06 September 2026 · Blackfire Real Estate & Builders
How big is 5 marla? Many housing societies count a marla as 225 sq ft, which makes 5 marla 25 × 45 ft; others use 250 sq ft (25 × 50 ft), and the revenue marla is 272.25 sq ft — check your allotment letter. Take a 25 × 50 ft plot: build on about 80% of it, put a first floor on top, add stairs and a mumty, and you have roughly 2,100 to 2,300 sq ft of covered area. Every cost figure you hear — "Rs 2,500 per sq ft", "Rs 1 crore complete" — is that number multiplied by a rate. So the first thing to fix is the covered area, not the rate.
What goes into the grey structure
The grey structure is the house before any finishing: foundations, walls, lintel band, roof slab, plaster, and the rough-in for plumbing, electrical and waterproofing. For a brick G+1 house of about 2,200 sq ft, the planning assumptions our cost tool starts from are:
- Bricks: about 30 per sq ft of covered area — 65,000 to 70,000 bricks.
- Cement: about 0.32 bags per sq ft — 650 to 750 bags of 50 kg, including plaster and tile bedding.
- Steel (sariya): 1.3 to 1.5 kg per sq ft — around 3 tons for a double-storey, more with a basement or long spans.
- Sand and crush: roughly 1.5 and 0.9 cu ft per sq ft.
- Labour: quoted per sq ft of covered area by the contractor on labour rate; ask what it excludes.
These are planning assumptions for an ordinary brick house. They have not yet been checked against Blackfire's completed projects, so treat them as a starting point, not a quotation. A house with an RCC frame, large openings or a basement needs its own bill of quantities from the structural drawing.
What finishing adds
Finishing is where two houses of the same size end up Rs 30 lakh apart: tiles, paint, doors and windows, sanitary, kitchen, wardrobes, electrical fittings, false ceilings and the front elevation. We estimate it per sq ft in three levels — economy, standard, premium — and the choice of tiles, kitchen and elevation moves the total more than anything in the grey structure.
How the total splits between grey structure and finishing depends mostly on the finishing level you choose, so get both priced before you compare quotes.
How to get a number you can defend
- Fix the covered area from the approved drawing, not the plot size.
- Phone two suppliers the same morning for cement, steel and bricks; rates change monthly.
- Get the grey-structure labour quote in writing with its exclusions (boundary wall, water and sewer connections, tank, termite treatment are usually extra).
- Decide the finishing level before you start — it changes the electrical and plumbing rough-in too.
- Keep 10% contingency.
Our construction cost by plot size tool does steps 1 and 5 for you and lets you type in your own supplier rates; the House Builder gives room-by-room tiles, paint, plaster and wire; the construction checklist tells you what to check at each stage before you pay.